PSE&G to upgrade gas facilities in Closter

Go

After PSE&G upgrades the gas lines in your neighborhood, we first wait for the ground to settle and then return to restore roads with permanent paving in accordance with each town's ordinance and paving requirements. Our goal is to complete this work with minimal impact to customers. Police will be directing traffic, and residents will be able to drive on the roads once the paving is complete. You will have access to your driveway throughout the work.

If you have any questions about the restoration process, you may call and leave a message at on our Gas Construction hotline at 833-661-6100

PSE&G is on schedule to start milling in Closter on Monday, October 29th, weather pending.  Estimated duration is approximately 3 days.  Milling is expected to occur on 10/29-10/30 and Paving on 10/31.  Please remember this work is weather dependent and the schedule may be adjusted if necessary.

Street

Between Streets

Demarest Ave

Durie Ave

Closter Dock Rd

Closter Dock Rd

Closter Dock Rd

1st St