PSE&G to upgrade gas facilities in East Orange

Go

Mid-March 2018 PSE&G will be working in East Orange to replace aging cast iron gas pipes with new, durable plastic and/or coated steel piping – ensuring the continued safety and reliability of our gas system well into the future.

Work will take place Monday through Friday between the hours of 7 a.m. and 5 p.m., with the potential for Saturday work. The gas main replacement and services portion of the work is expected to be complete by late fall 2018.

If you have questions please contact our dedicated GSMP line at 1-833-661-6200 and leave a message. Below is the streets where work will take place: Red (completed), Blue (In Progress), Green (Not yet started).

Street Between Street 1 Between Street 2
4th Ave N Grove ST End (West)
Central Ave S Maple Ave Hollywood Ave
Ely Pl 60' w/o Inclinton St 20' e/o Prospect St
Grove St Rutledge Ave Bloomfield Border
Kenmore Ter Cleveland Ter End
Lincoln St Prospect Ter Melmore Gdns
Maple Ave Park Ave Rutledge AVe
Mc Kay Ave Ross St Sanford St
Melmore Gdns (North Side) 190' w/o N Clinton St 60' e/o Lincoln St
Melmore Gdns (South side) N Clinton St 115' w/o Lincoln St
Oraton Parkway William St Park Ave
Park Ave Oraton Pkwy Maple Ave
PRW 10 220' w/o Prospect St End (West)
PRW 6 PRW 7 End
PRW 7 Prospect St End (West)
PRW 8 PRW 9 End
PRW 9 Prospect St End (West)
Rutledge Ave Maple Ave Grove St
 Rutledge Ave N Maple Ave Roosevelt Ave