PSE&G to upgrade gas facilities in Pequannock

Go

In early March PSE&G will be working in Pequannock to replace aging cast iron gas pipes with new, durable plastic and/or coated steel piping – ensuring the continued safety and reliability of our gas system well into the future.

Work will take place Monday through Friday between the hours of 7 a.m. and 5 p.m., with the potential for Saturday work. The gas main replacement and services portion of the work is expected to be complete at the end of April. The paving and street restoration will take place throughout the month of August.

If you reside on one of the streets listed below more information will be coming directly to your home.

If you have questions please contact our dedicated GSMP line at Oakland Gas 201-337-2519 and leave a message. Once the work has started you may also speak with the supervisor on site.

Below are the streets where work will take place: Red (completed), Blue (In Progress), Green (Not yet started)

Street Between Street 1 Between Street 2 Estimated Completion
Highland Ave Cedar Rd 495' N/O Cedar 6/1/2017
May Ave Cedar Rd Highland Ave 6/1/2017
Cedar Rd Elm Rd End 6/1/2017
Cedar Rd Elm Rd Highland Ave 6/1/2017