PSE&G to upgrade gas facilities in Riverton

Go

PSE&G will be working in Riverton to replace aging cast iron gas pipes with new, durable plastic and/or coated steel piping – ensuring the continued safety and reliability of our gas system well into the future.

Work will take place Monday through Saturday between the hours of 7 a.m. and 6 p.m., conditions permitting. The gas main replacement portion of the work is expected to be complete in December 2018. If you have any questions or concerns, please call our GSMP hotline at 1-833-661-6400.

Below are the streets where work will take place red (completed), blue (in progress), green (not yet started):

Street Town Between Street 1 Between Street 2
Linden  Riverton Bank Broad St.
7th St  Riverton Boro 70' n/o Maint St Cedar Ave
Cedar Ave  Riverton Boro 7th St Broad St
 Bank Ave  Riverton Boro  Linden Ave  Thomas Ave
 Bank Ave  Riverton Boro  Bank Ave  Broad St

PSE&G will also be working in Cinnaminson to replace aging cast iron gas pipes with new, durable plastic and/or coated steel piping – ensuring the continued safety and reliability of our gas system well into the future.

Starting early March 2018 work will take place Monday through Saturday between the hours of 7 a.m. and 6 p.m., conditions permitting. The gas main replacement portion of the work is expected to be complete in June 2018. If you have any questions or concerns, please call our GSMP hotline at 1-833-661-6400.

Street Between Street 1 Between Street 2
Taylors  160' n/o Burlington Pke 500' n/o PRW 18