PSE&G to upgrade gas facilities in Totowa

Go

In late April PSE&G will be working in Totowa to replace aging cast iron gas pipes with new, durable plastic and/or coated steel piping – ensuring the continued safety and reliability of our gas system well into the future.

Work will take place Monday through Friday between the hours of 7 a.m. and 5 p.m., with the potential for Saturday work. The gas main replacement and services portion of the work is expected to be complete in early September. The paving and street restoration will take place throughout the month of August.

If you reside on one of the streets listed below more information will be coming directly to your home.

If you have questions please contact our dedicated GSMP line at Clifton Gas 973-365-5314 and leave a message. Once the work has started you may also speak with the supervisor on site.

Below are the streets where work will take place: Red (completed), Blue (In Progress), Green (Not yet started)

 
Street Between Street 1 Between Street 2 Estimated Completion
Acorn St Wilson Ave Bogert St 6/1/2017
Bogert St Union Blvd Dewery Ave 6/1/2017
Dunkerly St Wilson Ave Bogert St 6/1/2017
Frances St Wilson Ave Garretson Ave 6/1/2017
Frances St Garretson Ave Bogert St 6/1/2017
Garretson Ave Frances St End 6/1/2017
Union Blvd Wilson Ave Bogert St 6/1/2017
Wentick St Wilson Ave Bogert St 6/1/2017
Wilson Ave Wentick St 50' n/o Frances St 6/1/2017