Building Your Solar Installation

Three Steps to Get Connected

PLEASE NOTE: PSE&G is not associated with any Solar Company and does not install or maintain solar systems.

Find out how to get approval to build your residential solar energy system and connect it to the PSE&G energy grid.

 Complete the three steps below to connect your residential solar energy system to the PSE&G electric grid.

Step 1: Interconnection Application Process

You or your renewable energy contractor will need to complete a net metering or interconnection agreement, as applicable. If the contractor completes the application, you, as the customer, must still sign the agreement.

  • Enter the address where your solar energy system will be located into our Solar Power Suitability Map
    This will preliminarily determine if the PSE&G electric circuits in the area will be able to accommodate your solar energy system.
  • Determine the level of your project as defined below.

Level 1
Certified Inverter-based Units of nameplate rating of 50kWAC or less and an export capacity of 25kWAC or less.

Level 2
Generators with export capacity less than or equal to 2,000kWAC.
*Customers proposing to install generation greater than 2,000 kWAC export are required to contact their EDC for the appropriate application procedures.  

Level 3

  • Export capacity greater than 2,000kWAC
  • Does not qualify for either the level 1 or level 2 interconnection review procedure
  • Where special relaying or metering is required

Contact us if you're unsure about your project level.

  • Submit the appropriate application. Note: the application process requires TWO parts. The second part of the application must completed after construction. It is discussed in Step 3 below.

Application Certified Inverter-based Units of nameplate rating of 50kWAC or less and an export capacity of 25kWAC or less

Application for Level 2 & Level 3 systems

  • Submit the application.

 

Level 1 applications

Email the application to CINETMETER@PSEG.com

 

Level 2 and Level 3 applications

When submitting Level 2/3 Attachment A interconnection requests, please email the Attachment A, Site Plan, Line Diagram, and PV Watts Calculator (NREL version only, please) to PSEG-CINetMeterLevel2@pseg.com

Please indicate “Commercial or Residential” in the subject line of your email so that it can be routed to the appropriate team for processing.

Additionally, if there is a non-utility transformer, please highlight it and indicate the configuration on the one line/3-line diagram accompanying your Attachment A submission.

You will no longer need to mail in an application and check for the interconnection fee to Construction Inquiry – Net Metering.  The interconnection fee will be invoiced upon creation of the notification for the interconnection request.  

In order to pay your invoice, you may go to https://nj.myaccount.pseg.com/user/login, or you may mail the invoice and payment to the address listed on the invoice.  Please do not forward net meter checks for invoiced notifications to the Net Meter Department, as they will be processed via the Customer Payment Processing Center (CPPC), as indicated on the invoice.

Application Information and Fees

Level

Specifications

Response

Cost

 

1

The facility is inverter-based

The facility has a nameplate rating of 50kWAC or less and an export capacity of 25kWAC or less. Complies with UL 1741 and IEEE 1547 design standards

Initial application within three business days. Interconnection response within 10 business days of when initial application review is completed.

No fee

2

Systems that qualify for Level 2

Complies with UL 1741 and IEEE 1547 design standards

*Customers proposing to install generation greater than 2,000 kWAC Export are required to contact their EDC for the appropriate application procedures.

Initial application review within three business days. Interconnection response within 15 business days of when initial application review is completed.

$50 plus $1 per kW of installed capacity

3

Does not meet the technical requirements for level 1 or level 2

Varies

$100 plus $2 per kW of installed capacity

 

Step 2: Preliminary Solar Project Approval Phase

  • Within three business days of receiving the interconnection application, PSE&G will contact you or your contractor to confirm that the review process has started.
  • The review period for Level 3 projects will depend on the degree of study needed. Additional documentation may be required.
  • After the EDC notifies the applicant that the initial application review is complete, within 10 business days for a Level 1 or within 15 business days for a Level 2 project, PSE&G will email notice of project approval or denial to you or your contractor. If the project is approved, you may move forward with the construction.

 

Note: DO NOT TURN THE SOLAR ENERGY SYSTEM ON UNTIL YOU RECEIVE A PERMISSION TO OPERATE (PTO) NOTICE FROM PSE&G (except for testing purposes).

 

Step 3: Construction and Final Approval Phase

  • Complete the application process. Upon completion of solar project construction, you or your contractor must send an approved Uniform Construction Code (UCC Certificate of Approval), Certificate of Completion, and as-builts to PSE&G.  Please email this documentation to:  PSEG-CINetMeterPart2@pseg.com, indicating “Commercial” or “Residential”, along with the notification number in the subject line.
  • The Certificate of Completion can be found in Part 2 of the Level 1 application or in Attachment B of the Level 2 and 3 application.
  • Within 5 business days of receiving the approved UCC Certificate of Approval, PSE&G will schedule an inspection. In certain locations, this appointment may be waived.
  • Upon receipt of UCC Certificate of Approval, within 13 business for a Level 1 application and 20 business days for Level 2 application, PSE&G will inspect the solar energy system. This inspection is mandatory for final approval. Part 2 fees will need to be paid before final inspection can be conducted.
  • During the inspection, if a meter change is deemed necessary by the inspector, your meter will be changed. You may lose power momentarily for this to occur.
  • Within five business days after successful completion of the EDC inspection, the EDC shall notify the customer-generator that it is authorized to energize the facility.
  • PSE&G will contact you or your contractor with the official outcome of the inspection. If the system passes inspection, you will receive a Permission to Operate (PTO) notice, which authorizes you to turn the system on. If the system fails inspection, you will be notified as to what actions need to be taken.

 

A SOLAR ENERGY SYSTEM THAT IS TURNED ON BEFORE RECEIVING A PTO POSES A SIGNIFICANT SAFETY HAZARD TO PSE&G ELECTRIC DISTRIBUTION WORKERS.

DO NOT TURN THE SYSTEM ON UNTIL YOU RECEIVE THE PTO.

Frequently Asked Questions